Bay Ridge Water Main Replacement – Councilman Brannan’s Message About Water and Suspended Alternate Side Parking
DDC Water Main Replacement Project in Bay Ridge
DDC = NYC Department of Design and Construction
Project begins April 3, 2018 – Expect intermittent water shut-offs.
TENTATIVE SCHEDULE (in order of project progression)
1- Colonial Road 89th Street – 91st Street Starts Monday April 2, 2018 Duration: 3 Days
2- 89th Street between Narrows and Colonial Road (Will start once Colonial Road is complete) Duration: 5 Days
3- Narrows Avenue 89th Street – Shore Road (Will commence following 89th Street work completion) Duration: 3 Weeks (due to manual excavation)
4- Shore Road 91st Street – Narrows Avenue Duration: 5 Days
Temporarily suspended Alternate Side Parking rules in the following areas through mid-May:
– Ridge Blvd from 89-91 (2 blocks)
– 88th St from Shore Road-Colonial Road (2 blocks)
– 87th St from Ridge Blvd-Shore Road (3 blocks)
Any questions, contact the DDC Community Liaison: Gina Modoo 718-238-1948